    Description

    The U.S. Department of Agriculture, specifically the Forest Service, is soliciting proposals for the BCLH Stewardship IRSC Phase 1 project, aimed at managing hazardous fuels and restoring access routes in the Willamette National Forest following the 2020 Beachie Creek and Lionshead fires. The project encompasses approximately 1,090 acres and includes mandatory tasks such as cutting and removing fire-killed timber, felling hazard trees, and performing road maintenance and reconstruction to ensure safe passage through affected areas. This initiative is critical for ecological restoration and public safety, emphasizing compliance with environmental regulations and community involvement. Interested contractors must submit their proposals by the specified deadlines, with the contract period running from August 4, 2025, to October 15, 2030. For further inquiries, contact Karen Ruklic at karen.ruklic@usda.gov or Heidi Andersen at heidi.andersen@usda.gov.

    Point(s) of Contact
    Karen Ruklic, Contract Specialist
    (208) 702-3519
    karen.ruklic@usda.gov
    Files
    Title
    Posted
    The "BCLH Stewardship IRSC Phase 1" RFP seeks to mitigate hazardous fuel risks in the Willamette National Forest following severe wildfires in 2020. The project focuses on clearing fire-damaged trees along critical access roads to restore safe passage through affected areas. Key activities include removing fire-killed timber, felling hazard trees, small fuel treatment near roadways, and road maintenance and reconstruction. Detailed specifications outline requirements for tree removal, including adjacent to Riparian Reserves and within Special Measure Areas that require additional protections. The RFP states the importance of environmental compliance, detailing operational restrictions based on seasonal factors, risk assessment, and cultural site preservation. Contractors must adhere to quality assurance protocols for inspections, and payment is contingent on work quality with defined acceptability levels. This initiative reflects the government's commitment to restoring forest health and ensuring public safety while managing ecological impacts effectively.
    The Willamette National Forest RFP (Request for Proposal) outlines the post-treatment fuel loadings for the BCLH Stewardship IRSC Phase 1 and Phase 3 projects within the Detroit Ranger District. The document presents a series of photographs illustrating the status of fuel treatments, with specific attention to fuel loads measured in tons per acre across various diameter size classes. In Phase 1, the fuel loads include 4.5 tons per acre for diameters of 0.25” to 3.0”, 6.8 tons for 3.1” to 9.0”, and 13.2 tons for 9.1” to 20”. The objective is to meet forest standards for fuel reduction while retaining larger downed wood greater than 16” in diameter on site. Conversely, Phase 3 indicated reduced fuel loads in smaller diameter classes but showed that the loading for the 9.1” to 20” class remained above minimum standards. This document serves as a guide for ensuring adequate fuel treatment levels in forest management projects, reflecting the government's commitment to forest health and wildfire risk reduction.
    The document outlines the Wage Determination No. 1977-0079 issued by the U.S. Department of Labor under the Service Contract Act. It specifies minimum wage rates applicable for contracts involving forestry and logging services in Oregon, emphasizing compliance with Executive Orders 14026 and 13658. Contractors must pay workers at least $17.75 per hour for contracts effective January 30, 2022, and $13.30 per hour for contracts awarded between January 1, 2015, and January 29, 2022, unless the wage rate listed is higher. Additional provisions detail required fringe benefits, including health and welfare contributions, vacation, holidays, and uniform allowances. The document mandates the process for any additional classifications not listed in the wage determination, outlining steps for contractors to request wage conformance. Furthermore, it highlights the requirements for paid sick leave under Executive Order 13706 for contracts awarded post-January 1, 2017. Overall, this document serves to ensure workers on federally contracted services receive fair wages and benefits, promoting labor standards compliance across contracts in the forestry sector in Oregon.
    The document outlines wage determinations for highway construction projects across Oregon, in compliance with the Davis-Bacon Act. It specifies minimum wage rates that contractors must pay, determined by the contract award date and under the guidelines of Executive Orders 14026 and 13658. For contracts initiated on or after January 30, 2022, the minimum wage is set at $17.75 per hour, while contracts from January 1, 2015, to January 29, 2022, require a minimum wage of $13.30 per hour unless otherwise specified. The document provides detailed classifications and corresponding wage rates for various labor categories, including electricians, laborers, welders, and truck drivers, along with additional zone pay based on project location relative to city hall benchmarks. The wage determinations are critical for federal contractors and subcontractors to ensure fair compensation, enhance worker protections, and comply with federal regulations. This document serves as a comprehensive reference for contractors involved with Oregon-wide construction projects, ensuring adherence to wage standards for all covered workers.
    The RFP: 12363N25R4001 outlines the timber removal specifications for the BCLH Stewardship IRSC Phase 1 project in the Willamette National Forest, specifically the Detroit Ranger District. Covering approximately 1,090 acres, the contract details the types of timber included for removal, classifications like standard, substandard, and damaged timber, alongside specific designations for clearcutting and selective harvesting. Payment rates for timber and regulations for transportation, operations, and safety are comprehensively defined to ensure environmental compliance and resource management. Key points include payment structures based on current contract rates, rigorous operational safety protocols, and maintenance of ecological integrity throughout the harvesting process. The contract emphasizes monitoring road conditions, enforcing limits during heavy rainfall, and adhering to established forest rules. The document's meticulous instructions are designed to guide contractors in managing timber resources sustainably while providing protections for various environmental and safety factors, reflecting governmental regulations and stewardship initiatives in forest management and resource utilization within federal frameworks.
    The BCLH IRSC Phase 1 document outlines essential road maintenance requirements for an upcoming timber sale project. It stipulates contractor obligations for pre-haul, during-haul, and post-haul maintenance across various road segments, ensuring compliance with specified standards. Each road segment is detailed with its respective distance and the applicable maintenance specifications for activities like brushing, surfacing, dust abatement, and snow removal. The document emphasizes contractor performance, including maintaining road safety and functionality, proper drainage, and managing vegetation and invasive species. Maintenance specifications also encompass a range of tasks from routine blading to specialized bridge maintenance, aiming to protect forest resources and maintain access for various vehicles. Key points include the necessity for documented material sourcing, seasonal maintenance practices, and procedures for snow and debris management. The purpose of this document aligns with federal and state requirements for road maintenance in timber sales, reflecting a focus on environmental stewardship and operational safety standards. The detailed specifications aim to facilitate efficient logging operations while safeguarding essential forest infrastructure.
    The document outlines the standard and supplemental specifications for the BCLH IRSC Phase 1 project, focusing on road construction and maintenance related to the Forest Service. It includes guidelines for materials, work execution, and safety measures compliant with federal standards. Significant sections cover excavation, embankment construction, soil erosion control, public traffic management, and contractor responsibilities. Key elements include compaction standards, the handling of construction materials, and traffic control protocols to ensure safety during road work. The document emphasizes environmental considerations, mandating weed-free materials and proper disposal of construction waste. Legal responsibilities and acceptance criteria for completed work alongside the need for thorough inspection and testing to guarantee conformity with contract requirements are also highlighted. Overall, the specifications aim to ensure a systematic, safe, and compliant approach to roadway construction within national forests, aligning with federal RFP guidelines and promoting stewardship of public lands.
    The document outlines the specifications and requirements for the BCLH IRSC Phase 1 project under the United States Department of Agriculture's Forest Service, focusing on road reconstruction within the Willamette National Forest. It includes signed approvals from multiple officials, indicating a collaborative effort in the project's planning. Key features of the document consist of general construction notes, drainage systems, fill repair tasks, and erosion control measures. The text emphasizes contractor responsibilities, including securing utility locates, repairing any damages incurred during operations, and adhering to specified erosion control timelines. A detailed estimate of quantities for base and optional items is provided. The document also outlines typical details for functional elements such as drainage installations, sediment control, and disposal area structures, along with typical installation techniques necessary for compliance with Forest Service standards. This project is part of broader federal initiatives aimed at maintaining infrastructure while ensuring environmental protection and safety, aligning with government RFPs and grant objectives. Collectively, it underscores the importance of sustainable practices in government-funded projects while adhering to legal and operational standards for public land management.
    The document addresses current federal and state requests for proposals (RFPs) and grants, emphasizing the government’s intent to solicit businesses for various projects and funding opportunities. It outlines the scope of these RFPs, focusing on both federal and state levels while detailing potential grants available to applicants. Key ideas include eligibility criteria, application processes, project goals, and compliance standards. By presenting specific project examples and outlining required qualifications, the document serves as a guidance tool for organizations seeking to engage with government contracts and funding. Ultimately, this file aims to streamline the proposal process, encourage participation from diverse entities, and ensure that projects align with government objectives to foster community development and resource management. In summary, it highlights the government's commitment to transparency and accessibility in its procurement and funding opportunities, facilitating collaborations that meet public needs.
    The document provides a detailed overview of geospatial data disclaimer from federal agencies including Esri, NASA, and the USDA Forest Service. It specifies that the geospatial data and maps supplied are not legal documents and do not guarantee merchantability or fitness for a particular purpose. Users are warned against using the data for determining land titles, legal ownership, or jurisdictional boundaries, as these data may not accurately reflect natural hazards. The document emphasizes that the data may change over time and it is the user's responsibility to verify its limitations and use it judiciously. Additionally, a graphical legend detailing a specific burn index classification is included, categorizing areas as unchanged, low, moderate, or high severity regarding burns. Overall, the document serves as a caution for users of geospatial data in accessing and employing this information responsibly to avoid misinterpretations or legal issues.
    The BCLH Stewardship IRSC Phase 1 RFP 12363N25R4001 outlines the acres impacted by varying levels of burn severity resulting from recent wildfires. The document details mandatory and optional project units, enumerating a total of 966 acres categorized by burn severity: low (0-25%), moderate (26-50%), and high (51-100%). Among the 966 acres, 166 acres are within 100 feet of roadways, which is specified as essential for the project’s scope. Mandatory units encompass the majority of higher burn severity acres, while optional units present a smaller portion of total burned land. The summary of these units indicates an extensive impact on ecosystems, necessitating restoration efforts in both mandatory and optional sectors. This analysis serves a vital component of federal and state funding proposals aimed at managing and recovering from wildfire damages, demonstrating a structured approach to prioritizing areas for rehabilitation according to burn severity. The data is crucial for developing effective restoration strategies and securing necessary federal and state grants or proposal funding for recovery initiatives in burnt landscapes.
    The document outlines the Amendment 0001 for RFP 12363N25R4001 regarding the BCLH Stewardship IRSC Phase 1 project, as discussed in a pre-proposal meeting held on June 30, 2025. The meeting, led by Karen Ruklic, the Contracting Officer, provided insights into project phases aimed at restoring the Opal Creek Scenic Recreation Area following recent disasters. The project is divided into three phases, with phase 1 being emphasized for its large scale and complexity. Key points include the importance of gathering proprietary cost data to justify timber value versus removal costs, discussions on road construction requirements to prevent environmental damage, and obligations such as payroll submissions and bonding requirements for the contractors. Special environmental regulations, particularly regarding the operation of mechanized equipment near water bodies and wilderness areas, were also highlighted. Overall, the document serves as a comprehensive guide for potential contractors, outlining requirements, deadlines, and logistical concerns necessary for bidding and project execution, ensuring compliance with federal regulations while enhancing community infrastructure and ecological restoration efforts.
    The BCLH Stewardship IRSC Phase 1 RFP outlines a comprehensive solicitation for hazardous fuels management and road reconstruction in areas impacted by the 2020 fires. This project, authorized under stewardship contracting authority, aims to mitigate risks from fire-killed trees and manage roadside fuels to restore access through affected regions. The contract entails multiple mandatory work tasks, including cutting and removing timber, hazard tree felling, small fuels treatment, and extensive road maintenance, with an estimated total cost for mandatory items ranging between $5-10 million and optional items between $100,000 and $250,000. Special measures are established to protect ecological areas and important habitats during operations, along with specified timeframes for work to ensure safety and regulatory compliance. Proposals must include a technical approach, past performance information, and a clear outline of the contractor’s plan to recruit local labor and procure community resources. Stricter guidelines are in place regarding safety measures, erosion control, and preservation of cultural resources. The emphasis on local community involvement and environmental protections illustrates a commitment to sustainable land management practices.
    The document details technical specifications and design guidelines for the BCLH IRSC Phase 1 project located in the Willamette National Forest under the USDA Forest Service. It outlines construction standards for wire facing and fill repair, specifically related to mechanically stabilized earth walls that align parallel to roadways. Key instructions include layering hardware cloth and backing materials, dimensions for various wire facing mats, and installation procedures to prevent backfill loss. Additional notes indicate the adherence to Hilfiker construction guidelines for forming and securing the structures. This document serves as an important reference for contractors and engineers tasked with executing the project, ensuring compliance with federal design and safety standards within the context of government contracting and infrastructure development.
    The document pertains to Amendment No. 1 for Solicitation No. 12363N25R4001, related to a stewardship contracting initiative managed by the USDA Forest Service. It outlines requirements for acknowledgment of this amendment by contractors, stipulating that offers must include references to the solicitation and be submitted before the specified deadline to avoid rejection. The amendment includes significant modifications, such as the addition of pre-proposal meeting documents, operational schedule amendments, and various corrections to previous statements regarding construction activities, including restrictions on vehicle usage during certain months and updated felling objectives. The period of performance for the project is indicated as August 4, 2025, to October 15, 2030. The document emphasizes compliance with existing forest regulations and necessitates careful oversight from the Contracting Officer. Overall, this amendment aims to clarify important operational guidelines and ensure that contractors are well-informed regarding expectations and requirements for the project's execution.
    The document is an amendment to solicitation number 12363N25R4001 for a stewardship contracting project involving the Detroit Ranger District of the Willamette National Forest. The amendment outlines several modifications to existing terms and requirements for contractors. Key changes include revised road use restrictions during specific seasons, modifications to the required disposal methods for woody debris, and adjustment of delivery quantities for logs. The contract period for this project is set from August 4, 2025, to October 15, 2030. The document stresses the importance of acknowledging receipt of the amendment to avoid the potential rejection of offers. It also clarifies that contractors must specify disposal methods in their technical proposals while emphasizing the project's focus on efficiency and cost-saving opportunities. Overall, this amendment reflects ongoing efforts to manage forest resources responsibly while ensuring compliance with federal contracting guidelines.
    The document details the Willamette National Forest's BCLH IRSC Project, managed by the United States Department of Agriculture Forest Service under the Detroit Ranger District. It presents three phases of project development, emphasizing road management and maintenance within the forest area. Each phase is accompanied by a vicinity map, outlining relevant National Forest System Roads (NFSR) and highlighting the connectivity and accessibility for environmental management and recreational usage. Phase 1 focuses on initial road work and layout; Phase 2 extends the efforts to additional roads identified for maintenance, while Phase 3 consolidates these developments. Each section includes specific NFSR numbers that correspond to the roads being managed, demonstrating the project's systematic approach to enhancing road infrastructure. This documentation serves as part of government planning and RFP processes intending to improve forest access while fostering compliance with federal regulations concerning forestry and land management. The comprehensive detailing of each phase suggests meticulous planning aimed at ecological conservation and infrastructural integrity within a significant natural reserve.
    The document outlines the procedure for contractors to obtain access to treatment units within the BCLH IRSC project area, which falls under a forest closure designation. Contractors must notify designated Forest Service officials—Heidi Andersen, Brett Blundon, and Darrin Neff—at least two working days in advance, especially considering potential delays during the holiday season. Following this, contractors will receive a road use permit and a risk assessment form, which must be completed and returned to the Forest Service. The Ranger will sign these documents and provide gate codes, granting access for the duration of the solicitation period. It is essential for contractors to carry the signed permit when accessing the area to avoid potential citations from the Marion County Sheriff's department. This document is crucial for ensuring compliance and safety while allowing authorized access to specific areas within the designated closure zone.
    The document relates to federal and state/local RFPs and grants, specifically outlining a series of identifiers, most likely corresponding to project numbers, contract codes, or reference materials associated with various initiatives. The primary focus appears to be on detailing systematic classifications within government procurement processes. The identifiers are organized numerically and potentially signify different categories or types of projects. The text seems to be a collection of alphanumeric codes, lacking descriptive content or context, which limits the accessibility of the information. Furthermore, the absence of context or metadata raises questions about the application of these identifiers in RFPs and grants, making it challenging to ascertain specific project details or funding parameters. This file is likely intended for internal use, serving as a reference guide for tracking or managing proposals and awards across various government sectors. The disjointed nature of the content suggests that additional explanation would be necessary for comprehensive understanding within the broader framework of government grants and procurement activities. Overall, the document serves an administrative function, outlining identifiers crucial for internal tracking and operations.
    The document outlines the road maintenance specifications and requirements for the BCLH IRSC Phase 1 timber sale project under the supervision of the Forest Service. It includes detailed prehaul, during haul, and post-haul maintenance guidelines for various road segments, including types of maintenance such as blading, surfacing, drainage provision, and vegetative management. Each section specifies the responsibilities of the Purchaser/Contractor to maintain roadway conditions, ensure drainage, and manage invasive species. Contracts include strict requirements for maintaining safe and effective travelways, including specific maintenance tasks outlined for different road segments, timeframes for such maintenance, and compliance with environmental regulations. The document emphasizes proper techniques for blading and vegetation cutting while ensuring minimal resource damage. Furthermore, it mandates comprehensive practices for applying water during operations, ensuring the material used is free of invasive species. This file serves as a critical reference for contractors involved in the project, ensuring adherence to both safety and environmental standards throughout the timber sale activities.
    The BCLH IRSC Phase 1 project on the Willamette National Forest aims to mitigate the hazards posed by fire-damaged trees along access routes, enhancing safety and access in areas affected by the 2020 fire. The project encompasses several key tasks, including removing hazardous fuel trees within 100 feet of roads, managing roadside vegetation, conducting road maintenance, and facilitating small fuels treatment within specified areas. Mandatory work items include cutting and removing fire-killed timber, felling non-commercial hazard trees within designated Special Measure Areas, and performing pre-haul, during-haul, and post-haul road maintenance. The document outlines detailed technical specifications, measurement criteria, and quality assurance standards to ensure compliance with government regulations. Acceptance and payment for work performed are contingent on meeting defined quality levels, with clear protocols established for inspections and potential rework. This project underscores the significance of forest management practices in reducing fire risk while also maintaining ecological and safety standards, showcasing the government's commitment to effective resource management in national forests.
    The BCLH IRSC Appendix B outlines timber removal specifications for a scaled stewardship contract in the Willamette National Forest's Detroit Ranger District. The document details the contract area, including maps and claims, and specifies diverse timber categories such as standard, substandard, and damaged timber. It provides guidelines on utilization, removal, and designations for clearcutting units, overstory, and understory removals, alongside timber volume estimates. Payment rates for various scenarios, including cuts made through mistakes or negligence, are established, ensuring clarity on financial responsibilities. Operational controls cover safety, logging conduct, and environmental protection, including erosion control measures and the treatment of logging debris. The document emphasizes adherence to safety and environmental regulations throughout the logging process, requiring regular inspections and accountability for scaling timber. Additional clauses address the continuity of contractor operations, payment liabilities, and conditions in the event of unforeseen circumstances or catastrophic damage. Overall, this summary captures the salient aspects of timber harvesting practices within the specified forest area, emphasizing compliance and stewardship principles.
    The BCLH IRSC Supplemental Specifications document outlines the guidelines and requirements for construction contracts under the jurisdiction of the Forest Service, US Department of Agriculture. It includes terms, scope, control of work, acceptance criteria, and legal relations. The document specifies the processes for bidding, contract execution, and performance standards pertaining to public traffic management, soil erosion, excavation, and material control. Key sections detail essential definitions, contractor responsibilities, and the regulations for maintaining public safety during construction activities. Particular emphasis is placed on adhering to environmental standards and ensuring that all materials are weed-free when brought onto national forest lands. The specifications aim to ensure that all construction practices meet federal standards while minimizing impact on public resources, highlighting the stringent nature of compliance necessary for successful project completion within the federal contracting framework.
    The document presents a detailed analysis of burn severity across various phases and units, indicating the extent of low (0-25%), moderate (26-50%), and high (51-100%) mortality acres resulting from wildfire impacts. Divided into three phases, the data showcases a total of 3,202.5 acres analyzed for burn severity, with Phase 1 accounting for 1,100.4 acres, Phase 2 for 1,076.3 acres, and Phase 3 for 1,025.8 acres. Each phase contains specific units, categorized as mandatory or optional, revealing the acres impacted by burn severity within 100 feet of roadways. The metrics are critical for understanding wildfire risks and guiding federal and state responses to environmental damage, aiding in RFPs and grant applications related to forest management and restoration efforts. This assessment underscores the significant environmental reporting needed to support recovery funding, facilitate effective resource allocation, and ensure compliance with governmental environmental standards during the rehabilitation of affected areas post-wildfire.
    The document outlines the limitations and legal disclaimers associated with the use of geospatial data provided by various federal agencies, including Esri, NASA, and the USDA Forest Service. It emphasizes that these data and maps are not legal documents and should not be used for definitive land ownership, boundary determinations, or assessments of natural hazards. Users are cautioned to verify the accuracy and reliability of the data, as changes may occur over time. The document mentions various agencies involved in creating or utilizing these geospatial datasets and includes a representation of the 2020 Composite Burn Index, categorizing vegetation burn severity. This information is relevant for government initiatives and funding proposals (RFPs and grants) that may require detailed environmental assessments and land-use analysis.
    This document outlines data regarding various land units, categorized by slope percentage and their corresponding acreage, indicating mandatory or optional statuses for management. The units include LH-11, LH-12, LH-56, and others, each classified based on slopes above or below 30%, with acreages specified. Mandatory units are required for certain phases (1 or 2), while optional units can be selected at the discretion of the managing agency. The distribution of land reveals a total of approximately 2,577 acres across different phases, with mandatory requirements amounting to 1,153 acres and optional management covering 1,424 acres. Individual unit assessments are critical for determining land use policy, compliance with environmental regulations, and the allocation of federal grants. This detailed categorization supports regional planning initiatives and reflects adherence to governmental guidelines concerning land conservation, resource management, and sustainable use, illustrating the project's intent to organize federal and local RFPs for effective land management and stewardship.
    The BCLH Stewardship IRSC Phase 1 project, located in Marion County, Oregon, focuses on hazardous fuel reduction and road maintenance following the fire-affected areas from the Beachie Creek Fire and the Lionshead Fire of 2020. The project encompasses mandatory and optional work activities that include cutting and removing fire-killed timber, hazard tree felling, small fuels treatment, and road reconstruction, aiming to restore access and safety in the region. The project requires contractors to provide detailed pricing for various service items and ensures compliance with federal regulations such as sustainable acquisitions and bonding requirements for construction. Contractors must register in the System for Award Management (SAM) to be eligible for bidding. The anticipated budget for mandatory activities ranges from $5 million to $10 million, and for optional tasks, it is between $500,000 and $1 million. The awarded contract will encompass work through 2028, with specified completion dates for different activities. This solicitation illustrates the Forest Service's stewardship contracting authority to effectively manage and rehabilitate national forest lands following significant wildfire impacts.
    The document outlines the specifications for a project concerning powerlines and wilderness management. It is structured to include mandatory and optional units, likely indicating various components for contractors to address in their proposals. There appears to be an emphasis on treatment units labeled with specific identifiers, suggesting a systematic approach to project execution. Additionally, a grid locator is referenced, which may denote geographic or operational boundaries for the work involved. The document seems to serve an administrative purpose, likely as part of a federal or local request for proposals (RFP), highlighting the need for contractors to be aware of environmental considerations, regulations, and specific operational guidelines. The focus on treatment units indicates an organized framework, which is crucial for bidders in understanding the scope and nature of work required for governmental compliance and project success. Overall, the document emphasizes structured project management and regulatory adherence in public sector work related to infrastructure and environmental resources.
    The document outlines the management plan for the ÆQ Campground, focusing on timber removal and forest management activities. It includes various components such as mandatory and optional units detailing the processes for cutting and removing included timber, consulting on fall and leaving practices, and addressing fall hazard trees. The management plan is structured to adhere to specific treatment units and regulations, emphasizing the responsibilities of contractors in safeguarding areas like trailheads and picnic sites. A topographical map accompanies the plan, highlighting treatment units, roadways, and targeted areas for tree removal. This initiative reflects a broader effort in federal and state forestry management, aiming to ensure ecological safety while improving recreational areas through strategic resource management. Compliance with these guidelines is vital for contractor selections in response to RFPs and grants related to environmental conservation and public land management.
    The ÆQ Campground document outlines specific guidelines for tree removal as part of forest management practices. It specifies mandatory and optional items related to the cutting and removal of timber, particularly focusing on the management of hazardous trees and the consultation of the area's ecological balance. The designated treatment units are marked and detailed on accompanying maps, indicating the locations of gates, picnic sites, and trailheads within the campground. The project also outlines restrictions on operations during the prime wildlife nesting period from March 1 to July 15, ensuring compliance with environmental regulations. This document is integral for government planning to maintain safety and ecological integrity within public recreational areas while facilitating necessary forestry activities. Overall, it provides structured protocols for natural resource management linked to federal guidelines.
    The document outlines a project plan for tree removal and management at ÆQ Campground, focusing on safety and ecological preservation. The plan includes various treatment units where specific timber-related tasks are mandated, such as cutting and removing included timber, and addressing fall hazard trees. Mandatory and optional items are delineated, indicating which tasks must be executed and which are recommended based on the elevation maps provided. Key areas of the campground, including gates, picnic sites, and trailheads, are identified alongside a wilderness area, reflecting the importance of protecting certain locations during operations. The document is structured with maps indicating treatment units and operational guidelines for safely managing timber by 2025. This project is essential for enhancing forest health while ensuring safety and compliance in line with federal and state regulations for campground management. The overall goal is to implement effective forest management practices that address ecological integrity while providing recreational opportunities.
    The document outlines the ÆQ Campground project, focusing on timber management and tree removal within a federally designated area. It includes mandatory and optional treatment units, specifying protocols for cutting and removing included timber, consulting on fall and leave strategies, and addressing hazardous tree removal. Each treatment unit is identified with specific designations and mapped coordinates, indicating their location in relation to the campground's infrastructure, such as gates, picnic sites, and trailheads. The document indicates a "No Operations" period from March 1 to July 15, emphasizing time-sensitive management of the forestry activities. The overarching goal appears to be forest health improvement and safety enhancements within the recreational site, which is critical for both environmental stewardship and future recreational use. The careful planning and mapped guidelines reflect compliance with federal and state regulations regarding recreation areas and timber management practices.
    The ÆQ Campground document outlines a project involving the management and removal of trees within designated treatment units in a wilderness area. It specifies mandatory and optional tasks related to timber removal, including the cutting and disposing of included timber and the management of hazardous trees. The treatment units, delineated on a detailed map, highlight areas for operations scheduled from March 1 to July 15. Additionally, the project emphasizes the need to protect designated trails and complies with established tree removal guidelines. This initiative aims to enhance safety and environmental management in federal and state-managed lands, aligning with government goals for resource management and conservation. The document's structure integrates maps and treatment units, underscoring logistical details essential for project execution and oversight.
    The ÆQ Campground document outlines proposed treatment activities for a designated wilderness area, specifically focusing on tree removal and related protocols. It identifies mandatory and optional tasks, including cutting, removing timber, and managing fall hazard trees, with specific items outlined under three treatment units (SMA 1, SMA 2, and SMA 3). The document includes a map indicating the campground's layout, highlighting a trail to protect, and marking various sites such as picnic areas and trailheads. The inclusion of powerlines and treatment units, along with operational mandates from March to July, emphasizes a structured approach to forestry management. This document is part of federal and state RFPs aiming to maintain environmental integrity while ensuring safety and compliance in forest operations. The outlined activities and guidelines illustrate the government's commitment to sustainable wilderness management practices.
    The ÆQ Campground file outlines treatment units for environmental management focused on timber removal and trail protection, specifically designed for agency operations between March 1 and July 15. It details mandatory and optional tasks, including cutting and removing timber, consulting and leaving fallen hazards, and farther removal of all categories of hazard trees. A map indicating the treatment units of the campground includes designated picnic sites, trailheads, and powerlines, emphasizing the management of natural resources within designated areas. The specifications include mandatory and optional items, which are structured around operational guidelines for contractors or agencies involved in timber and ecological management. This document is essential for informing potential applicants in response to federal or local requests for proposals (RFPs) and grants aimed at forest and land management, ensuring adherence to regulatory frameworks and environmental safety standards.
    The ÆQ Campground document outlines specific forest management activities to be carried out in a designated treatment unit as part of a government Request for Proposals (RFP). It highlights mandatory and optional tasks related to timber management, including cutting, removal, and consultation for hazardous tree management. The document details a timeline for operations (March 1 to July 15) and provides a map indicating key features such as picnic sites, trails, and power lines. Specific units for timber treatment are categorized, with guidelines for tree removal. The aim is to enhance forest health and safety through structured management, emphasizing the importance of following protocols to address environmental and safety standards within the campground area. This information is critical for potential bidders seeking to comply with federal and state guidelines in forest management proposals.
    The document outlines a timber management project at ÆQ Campground, focusing on various mandatory and optional tree removal operations within specified treatment units. The project includes delineated areas for timber cutting, removal of hazardous trees, and assessments for certain mandatory tasks, all scheduled between March 1 and July 15. Specific guidelines detail the processes for cutting and leaving timber, consulting tree management standards, and designating protected trails. Additional elements include mapped treatment units and measurements for operational areas, as well as a status description indicating non-operation periods. The proposal aligns with government RFPs, ensuring environmental considerations in forest management and promoting safety and ecological balance. Overall, this initiative is aimed at responsible ecological stewardship while engaging for federal and local compliance.
    The ÆQ Campground document outlines guidelines for timber management and maintenance within the designated area, focusing on specific tasks to enhance the campground's environment. It identifies mandatory and optional measures, including cutting and removing included timber, consulting and leaving for specific management areas (SMA1, SMA2, SMA3), and handling hazardous trees. The document details treatment units, operational timelines, and a map indicating various points such as gates, picnic sites, and trailheads crucial for protection during timber operations. This structured approach emphasizes preserving wilderness and associated resources while facilitating safe management practices. The document serves as a reference for contractors and organizations involved in maintaining campground facilities and aligns with government objectives regarding environmental stewardship and public safety in natural areas.
    The document outlines the management plan for the ÆQ Campground's woodland area, detailing timber removal and tree management operations. The plan specifies mandatory and optional tasks, including cutting and removing included timber, consulting on fall and leave practices, and addressing fall hazard trees. It provides a time frame for operations (March 1 to July 15) and delineates treatment units on an accompanying map. Additionally, the plan categorizes tasks related to tree management and outlines specific guidelines for tree removal, aligned with wilderness protection measures. This initiative reflects the federal government's commitment to sustainable forestry practices and the maintenance of recreational areas, ensuring public safety and environmental conservation within state and local jurisdictions. The document serves as a crucial reference in the context of government RFPs and grants, illustrating prioritization of woodland management and community recreation space retention.
    The document outlines the specifications for a timber management project at ÆQ Campground, focusing on tree removal and maintenance during a designated operational period, specifically from March 1 to July 15. It categorizes tasks into mandatory and optional units, including the cutting and removal of specified timber, consulting, and managing fall hazard trees. Visual aids, like a map detailing various treatment units, roads, and access points, complement the written instructions. The project exemplifies a federal initiative aimed at ecological management and infrastructure improvement within recreational areas, ensuring compliance with strict guidelines for environmental safety and land usage. The document emphasizes the importance of careful planning and adherence to protocols for tree removal and hazard management in natural settings.
    The document outlines a tree removal project at ÆQ Campground, detailing specific operations scheduled between March 1 and July 15. It categorizes various types of tree removals into mandatory and optional units, specifying tasks such as cutting and removing timber, falling hazard trees, and managing specific tree types within designated treatment units. Visual aids, including maps, illustrate the campground layout, highlighting access points like gates, picnic sites, and trailheads, alongside locations of powerlines and wilderness areas. The document's structure combines operational instructions with geographic references, emphasizing compliance with guidelines for environmental management and safety during the timber treatment procedures. This initiative aligns with government efforts to enhance outdoor facilities while maintaining ecological integrity, indicative of federal and state commitment to sustainable land management practices.
    The document outlines a proposal for tree management activities in a designated campground area. It categorizes various treatment units for timber removal, including mandatory and optional tasks, targeting the cutting and removal of included timber and hazardous trees. Specifically, it distinguishes between mandatory units (e.g., cutting, consulting on hazardous trees) and optional units, with a focus on preserving wilderness areas, powerlines, and safe public access through picnic sites and trails. The document includes maps indicating treatment unit locations and emphasizes maintaining safety protocols during operations scheduled from March 1 to July 15. The overall purpose of the document is to solicit bids for managing forest resources effectively while adhering to federal guidelines and promoting environmental conservation. This reflects broader government efforts to maintain healthy ecosystems and prevent hazards in public recreational areas.
    The ÆQ Campground document outlines a tree removal and management proposal, focusing on several treatment units designated for forestry operations. It specifies mandatory and optional items concerning the cutting and removal of timber, consultation and assessment for hazard trees, and the responsibilities of contractors in managing tree fall and leave processes. The mapped areas involve locations such as picnic sites and trailheads while also accounting for nearby powerlines and wilderness zones. The treatment plan emphasizes essential safety measures, as operations are restricted during a non-operational time frame from March 1 to July 15. The project reflects a commitment to environmental management in federal RFP and grant processes, underscoring the importance of organized tree removal activities to maintain the campground's ecological balance and safety for recreational areas. Key points include treatment unit numbers, specific guidelines for tree removal, and paths for protection that enhance the campground's usability and safety.
    The document outlines specifications for tree removal and maintenance operations within ÆQ Campground, focusing on designated treatment units. It includes mandatory and optional tasks such as the cut and removal of included timber, consultations for fall hazards, and the removal of hazardous trees. The timetable for operations is specified as March 1 to July 15, emphasizing compliance with forest management practices. Various treatment units are denoted by corresponding numbers on a map, indicating specific trails and picnic sites that require protection during these activities. The document is a reference for contractors responding to requests for proposals (RFPs) or grants related to campground maintenance and forest management, highlighting environmental stewardship objectives while ensuring safety within recreational areas. Proposed actions are categorized to provide flexibility in implementation based on necessity and available resources.
    The document outlines a project related to timber management at ÆQ Campground, detailing specific treatments and guidelines for the removal and management of hazardous and non-hazardous trees within the site. It specifies mandatory and optional tasks for contractors, such as cutting and removing included timber and addressing fall hazard trees. A map accompanies the guidelines, highlighting treatment units, existing features like gates, picnic sites, and trails, as well as the designated timeline for operations which runs from March 1 to July 15, indicating limited operational hours. The document emphasizes the importance of safety and adherence to environmental protocols in managing timber resources within recreational areas, suggesting a structured approach typical of federal grant requests and local proposals aimed at preserving wilderness while ensuring public safety. Overall, this file serves as a directive for contractors to follow in executing timber management practices effectively while meeting regulatory standards.
    The ÆQ Campground document outlines a comprehensive plan for a forestry project involving tree removal and hazard mitigation within designated treatment units. The primary focus is on specific tasks such as cutting and removing timber, falling hazard trees, and maintaining trails, with certain tasks categorized as mandatory and optional. The work is structured into various units, each with distinct requirements and timelines, particularly stressing the no-operation period from March 1 to July 15. The project emphasizes compliance with established guidelines for tree removal to ensure safety and environmental protection. The inclusion of maps detailing treatment unit boundaries and relevant infrastructure, such as roads and power lines, supports the logistical aspects of the proposal. Overall, the document serves as a framework for managing forest health and recreational site safety, aligning with government efforts in land management and resource conservation.
    The ÆQ Campground document outlines a project involving timber management and hazard tree removal within designated treatment units. The project consists of both mandatory and optional tasks, including the cutting and removal of included timber, consultation, and the falling of hazard trees, with varying requirements based on the specific management areas designated as SMA1, SMA2, and SMA3. A map accompanies the document, detailing the campground layout, including picnic sites, trailheads, and powerline locations, along with the designated areas for tree removal and protection. This initiative reflects compliance with federal and state guidelines for forest management, aiming to enhance safety and environmental stewardship within the campground area. The timeline specifies a non-operation period from March 1 to July 15, emphasizing the seasonal considerations relevant to the project. The document serves as a foundation for federal RFPs related to resource management and conservation efforts.
    The document outlines a detailed plan for timber management at the ÆQ Campground, focusing on tree removal and hazard tree management in various treatment units designated for forestry operations. The project categorizes tasks into mandatory and optional units, including cutting and removing included timber, consulting on fall and leave techniques, and addressing hazardous trees. Specific management units are highlighted, indicating operational timelines, geographical boundaries, and included features like trails and picnic sites. The map within the file delineates important locations and treatment units that are subject to regulations and safety considerations, essential for maintaining the campground's integrity and safety during the operations. This initiative reflects the government's commitment to forest management and the maintenance of recreational areas through structured timber treatment, ensuring compliance with environmental standards while enhancing public facilities.
    The document outlines a project related to tree removal and maintenance in a designated campground area, specifically the ÆQ Campground. It details various mandatory and optional tasks categorized as treatment units, including cutting and removing timber, consulting on fall hazards, and managing tree health. The operations are scheduled for a specific timeframe, with a clear distinction between mandatory units required for compliance and optional units that can be addressed at discretion. The document includes reference maps for context, indicating the locations of trails, picnic sites, and powerlines within the campground. The structure of the document indicates adherence to federal and local guidelines for environmental stewardship, ensuring that tree removal aligns with maintaining safety and protecting wilderness areas. Overall, this project reflects the government's effort to maintain campground safety while regulating timber management practices, which are essential for federal grant and RFP compliance.
    The document outlines the management and treatment plan for the ÆQ Campground, focusing on timber maintenance and trail protection efforts. It specifies mandatory and optional tasks, including the cutting and removal of included timber, consultation on fall hazards, and the felling and leaving of designated trees. The operational schedule demands adherence to non-operational periods, specifically from March 1 to July 15, for safety and environmental considerations. The material also contains critical mapping data, showcasing various site features such as picnic areas, trailheads, and powerline locations, aimed at guiding treatment unit operations. Detailed tree removal guidelines are included to ensure systematic management of forestry within the campground. The document serves as a reference for compliance with federal and state regulations related to land use and natural resource management in preparation for potential federal grant or RFP applications centered around campground maintenance and environmental stewardship. Overall, it is a structured approach to manage natural resources efficiently while maintaining campground safety and accessibility.
    The ÆQ Campground document outlines a proposed project for tree removal and management in designated areas within a campground setting. It specifies mandatory and optional treatment units, including the cutting and removal of included timber and the consultation for fall and leave activities concerning hazardous trees. The map included, referred to as "Map 5 of 27," indicates critical roads, trail protection measures, and relevant treatment units that need to be addressed between March 1 and July 15, highlighting a no operations period. This document serves as a blueprint for potential contractors, detailing the scope of work for forest management and safety measures aimed at maintaining ecological integrity and visitor safety. The presence of the mapped area and outlined treatment units further underscores the importance of compliance and strategic planning in response to environmental needs within federal and state park systems.
    The document outlines the ÆQ Campground project, focusing on specific forest management tasks, including timber removal and tree hazard assessments. Key components include mandatory and optional tasks, such as cutting and removing included timber, consulting on safety measures (SMA), and addressing fall hazard trees, with a delineation of treatment units and operational dates (3/1-7/15). The document annotates geographic features like gates, picnic sites, trailheads, and powerlines, played out on a map indicating the specific treatment areas identified as BCLH Phase 1. The regulations specified are part of federal grants and RFPs aimed at maintaining wilderness areas and ensuring public safety through forest management practices. The overall aim is to facilitate sustainable land use while preventing hazards in the campground surroundings.
    The document outlines the tree removal and management guidelines for the ÆQ Campground project, highlighting specific tasks related to timber management in designated treatment units. Key components include the management of hazardous trees, the cutting and removal of included timber, and consultation measures for fall hazards, which are categorized into mandatory and optional tasks. The document also identifies various units and landmarks such as picnic sites, trailheads, powerlines, and wilderness areas, providing a detailed map for reference. The project operates within established timeframes, specifically excluding operations between March 1 and July 15. This structured approach ensures compliance with environmental management standards while focusing on safety and efficiency in tree management practices. The report serves as a groundwork for federal and state-level requests for proposals (RFPs) and grants aimed at environmental stewardship and resource management.
    The ÆQ Campground document outlines a proposed project focusing on forest management practices involving tree removal and hazard mitigation. It specifies treatment units labeled with mandatory and optional tasks, including cutting and removing timber, consulting fall and leave protocols for specific tree management, and addressing hazardous tree removal. The document is structured with visuals such as maps indicating the campground layout, including picnic sites and trails. The presence of powerlines and wilderness areas is noted, along with designated no operations periods from March 1 to July 15. This project aims to enhance safety and ecological integrity within the campground, aligning with federal and state regulations on forest management and environmental protection. The plan emphasizes careful planning and execution to mitigate hazards while maintaining land management objectives.
    The document outlines a governmental project concerning the management of timber and hazard trees in a designated wilderness area, delineated in treatment units. It includes a range of operations under a federal Request for Proposals (RFP) framework, specifying mandatory and optional tasks related to tree removal, including cutting, removing, and consulting on hazard trees. The document provides a visual representation with maps highlighting locations of gates, picnic sites, and trailheads, emphasizing the areas affected by powerlines and wilderness. Key operational tasks include the command to cut and remove included timber, manage the consultation process for tree hazards, and ensure compliance with specific guidelines during the implemented procedures. All tasks are categorized into mandatory and optional units and are scheduled for non-operation periods, particularly from March 1 to July 15. This project aligns with federal land management objectives, aiming to improve safety, preserve environmental integrity, and combat ecological hazards within park lands, thereby supporting community recreational areas and conserving natural resources.
    The BCLH Stewardship IRSC Phase 1 project, issued by the USDA Forest Service, seeks contractors to perform comprehensive land management activities in response to hazards caused by the Beachie Creek and Lionshead fires of 2020. The contract focuses on cutting and removing fire-killed timber, maintaining and reconstructing roads, and managing hazardous fuels within designated areas, particularly near access routes vital for recovery. The project spans 1,090 acres in Marion County, Oregon, with specific milestones for the completion of mandatory and optional activities, emphasizing environmental protection during operations. Contractors must comply with federal regulations, including the Service Contract Act, and provide pricing proposals for a variety of services while ensuring timely project completion by set deadlines. Special consideration is given to sustainable practices and the use of biobased or environmentally friendly products throughout the project's execution. Quality control measures will be enforced to ensure compliance with project specifications, with periodic inspections by the government to guarantee satisfactory performance. The contractor’s detailed operational plans and adherence to wildlife and seasonal restrictions are critical to the success and ecological integrity of the project.
    The BCLH Phase 1 Stewardship IRSC site visit, held on November 4, 2024, aimed to prepare contractors for upcoming solicitations related to the removal of hazard trees following the 2020 Beachie Creek and Lionshead fires. The meeting, led by USDA Forest Service officials, highlighted the need to address hazardous fuels and reconstruct roads while accommodating contractor concerns regarding bonding requirements. The project has been divided into three phases due to previous feedback, aiming to enhance competition through manageable contract values and performance periods. Notably, the solicitation timeline is set to begin in early 2025, with contract awards anticipated by mid-2025. Contractors provided input on operational preferences for wet weather work, with discussions surrounding the integration of mechanized harvesting equipment under specific conditions. The comprehensive approach aims not only to restore land but also to assist rural economies, ensuring that small businesses can participate alongside larger firms. Overall, this initiative underscores the critical need for effective project management, safety considerations, and environmental compliance throughout the recovery efforts in the affected areas.
    Lifecycle
    Title
    Type
    Presolicitation
    Similar Opportunities
    End of the World Long Term Stewardship
    Agriculture, Department Of
    The U.S. Department of Agriculture, specifically the Forest Service, is seeking industry feedback through a Request for Information (RFI) for the End of the World Long Term Stewardship project in the Nez Perce-Clearwater National Forest, Idaho. The initiative aims to address forest health by reducing risks associated with insect infestations, wildfires, and improving water quality across approximately 17,000 acres, with an anticipated offering of over 50 million board feet of commercial timber. This project is significant for enhancing forest resilience and fostering sustainable land management practices, with various service activities including timber removal, road maintenance, and biomass management planned over a potential 10-year contract term. Interested parties are encouraged to submit their feedback by September 17, 2025, and can direct inquiries to Matt Daigle at matthew.daigle@usda.gov or by phone at 605-415-9057.
    Intermountain Stewardship BPA
    Agriculture, Department Of
    The U.S. Department of Agriculture, Forest Service is seeking proposals for the Intermountain Stewardship Blanket Purchase Agreement (BPA), aimed at enhancing forest health and managing hazardous fuels across multiple National Forests in Idaho, Nevada, Utah, and Wyoming. The BPA will facilitate various stewardship activities, including timber removal, road maintenance, and restoration projects, with a focus on sustainable forest management and wildfire risk reduction. This initiative is critical for supporting local economies and ensuring compliance with federal environmental regulations. Interested contractors must submit their proposals by April 12, 2023, and are required to be registered in the System for Award Management (SAM) to be eligible for award. For further inquiries, contact Matt Daigle at matthew.daigle@usda.gov or Mark T. Phillipp at mark.phillipp@usda.gov.
    Wallowa Whitman National Forest, La Grande Ranger District 2026 Fuels Reduction Fall Viewing
    Agriculture, Department Of
    The U.S. Department of Agriculture's Forest Service is seeking small business contractors for the Wallowa Whitman National Forest's 2026 Fuels Reduction Fall Viewing project in La Grande, Oregon. This opportunity involves a site visit for interested vendors to assess the project areas prior to the issuance of a full solicitation, aimed at enhancing forest health and resilience to improve wildfire suppression efforts across multiple project areas, including Sheep, Sandbox, Cove, Mt. Emily, and others. The project encompasses various thinning and piling treatments across 1,875 acres of lop and scatter thinning, 2,125 acres of thin and hand piling, and additional methods to create defensible space for local communities and reduce wildfire risks. Interested parties can contact Andrea J. Pollock at andrea.pollock@usda.gov or Terry George at terry.george@usda.gov for further information.
    Bitterroot Front 10 Year G-Z IRSC
    Agriculture, Department Of
    The U.S. Department of Agriculture, Forest Service is seeking qualified contractors for the Bitterroot Front 10-Year Integrated Resource Stewardship Contract (IRSC), aimed at enhancing forest restoration and reducing wildfire risks across approximately 13,000 acres in Montana. The contract will involve various service activities, including timber removal, road maintenance, and biomass removal, with an anticipated offering of at least 90,000 CCF of commercial timber over the contract's duration. This initiative is crucial for bolstering the region's wood utilization capacity and ensuring a consistent supply of wood products while adhering to environmental regulations and safety standards. Interested parties can contact Matt Daigle at matthew.daigle@usda.gov or call 605-415-9057 for further details, and a site visit is scheduled for October 28, 2025, to discuss the project in depth.
    NORTHERN ROCKIES STEWARDSHIP BPA
    Agriculture, Department Of
    The U.S. Department of Agriculture, specifically the Forest Service, is soliciting proposals for the Northern Rockies Stewardship Blanket Purchase Agreement (BPA) aimed at conducting stewardship activities across multiple national forests in Idaho, Montana, North Dakota, and South Dakota. The BPA will facilitate various land management projects, including timber harvesting, hazardous fuels reduction, and restoration activities, with a focus on enhancing forest resilience and improving watershed health. This procurement is crucial for sustainable forest management and aims to provide local communities with wood resources while minimizing fire hazards. Interested contractors must submit their proposals by April 20, 2023, and ensure they are registered in the System for Award Management (SAM). For further inquiries, contact Matt Daigle at matthew.daigle@usda.gov or 605-415-9057.
    Deschutes NF - West Bend Rock Road Closure
    Agriculture, Department Of
    The Department of Agriculture, specifically the Forest Service, is seeking qualified vendors for the West Bend Rock Road Closure project on the Deschutes National Forest, located in Bend, Oregon. The primary objective of this procurement is to decommission and close roads to improve wildlife habitat by reducing open road densities, which will enhance habitat quality and connectivity. This project involves road obliteration and entry management treatments, including subsoiling and constructing barriers to prevent vehicle access, and is set aside for total small business participation. Interested contractors must submit their price quotes and necessary certifications by January 7, 2026, at 4:30 PM PT to Andrea Pollock at andrea.pollock@usda.gov, with the contract expected to be awarded based solely on price, and work completion anticipated by December 1, 2026.
    Pacific Southwest (PSW) STEWARDSHIP BPA (R5 Multiple Forests)
    Agriculture, Department Of
    The Department of Agriculture, specifically the Forest Service, is seeking proposals for the Pacific Southwest (PSW) Stewardship Blanket Purchase Agreement (BPA) to support various land management activities across multiple National Forests in California. This BPA aims to facilitate hazardous fuels reduction, restoration work, and other stewardship activities, with a focus on improving forest health and ecosystem vitality while addressing local community needs. The BPA will remain open for proposals throughout its 10-year term, with the possibility of extension up to 20 years, and will allow for multiple awards based on technical and pricing evaluations. Interested contractors must be registered in the System for Award Management (SAM) and submit their proposals via email to the designated contacts, Matt Daigle and Mark Phillipp, with the solicitation remaining active until December 31, 2032.
    Wallowa Whitman National Forest Snow Park Snow Plowing
    Agriculture, Department Of
    The Department of Agriculture, specifically the USDA Forest Service, is seeking qualified contractors to provide snow plowing services for the Wallowa-Whitman National Forest Sno-Parks located in Baker City, Oregon. The contract, identified as RFQ 1240BE26Q0014, is structured as an Indefinite Delivery/Indefinite Quantity with Firm Fixed Price CLIN, covering a base year from November 20, 2025, to September 30, 2026, along with five optional renewal years. These Sno-Parks serve as critical access points for winter recreation and special use operations, necessitating timely snow removal to ensure safety and accessibility for the public. Proposals must be submitted via email by 4:30 PM PST on December 22, 2025, and should include a technical quote, price quote, and necessary certifications, as the government intends to award the contract based on these submissions without further discussions. Interested parties can contact Andrea J. Pollock at andrea.pollock@usda.gov for additional information.
    Forest Service - Groveland Storm Damage Repair
    Agriculture, Department Of
    The U.S. Department of Agriculture, through the Forest Service, is soliciting proposals for the Groveland Storm Damage Repair project located in the Stanislaus National Forest, California. This total small business set-aside contract, valued between $500,000 and $1,000,000, aims to repair landslides on two Forest roads, involving tasks such as constructing retaining structures, re-establishing road prisms, resurfacing, and implementing erosion control measures. The project is critical for restoring access and safety to the affected areas following damage from severe weather events in 2023. Proposals are due by January 12, 2026, at 11:00 AM PDT, with a mandatory site visit scheduled for January 6, 2026. Interested contractors should direct inquiries to Tanya Torres at tanya.torres@usda.gov and are required to adhere to various performance and bonding requirements throughout the project duration.
    OR FS DSHUT601 60(1), Road 60 Improvements, MP 0 - 1.0
    Transportation, Department Of
    The Department of Transportation, through the Federal Highway Administration, is seeking bids for the OR FS DSHUT601 60(1) Road 60 Improvements project, located approximately 14 miles west of Gilchrist, Oregon. This project involves grinding, paving, and striping approximately 1.02 miles of roadway, with an estimated cost between $700,000 and $2,000,000, and a tentative completion date set for Summer 2026. The improvements are crucial for enhancing road safety and infrastructure in the area, and the contract will be awarded as a sealed bid, firm-fixed-price arrangement. Interested vendors should register on SAM.gov to receive notifications about the solicitation documents, which are expected to be released in early 2026, and can contact the Contracts G. Office at wfl.contracts@dot.gov or by phone at 360-619-7520 for further inquiries.