Trinity River Division GSU Transformer Replacement
ID: 140R2024R0002Type: Sources Sought
Overview

Buyer

INTERIOR, DEPARTMENT OF THEBUREAU OF RECLAMATIONMP-REGIONAL OFFICESACRAMENTO, CA, 95825, USA
Timeline
    Description

    The Department of the Interior, through the Bureau of Reclamation, is seeking bids for the replacement of Generator Step-Up (GSU) transformers at three power plants as part of the Trinity River Division in California's Central Valley Project. The project involves the supply, installation, and commissioning of nine transformers, along with associated components such as surge arresters and bus systems, while ensuring compliance with safety and environmental regulations. This initiative is crucial for modernizing the electrical infrastructure and maintaining uninterrupted power generation during the replacement process. The estimated contract value ranges from $35 million to $50 million, with proposals due by January 31, 2025. Interested bidders can contact Matthew Thomas at mthomas@usbr.gov or call 916-978-5117 for further information.

    Point(s) of Contact
    Thomas, Matthew
    (916) 978-5117
    (916) 978-5175
    mthomas@usbr.gov
    Files
    Title
    Posted
      Procuring: Advanced Machine Learning and AI capabilities for FBI's Criminal Investigative Division to enhance its analytical capabilities in the following 3 areas: 1. Network Analysis: Enhancing the ability to visualize and analyze relationships between entities of interest. 2. Geospatial Analysis: Improving the understanding of geographic patterns and trends related to criminal activities. 3. Dark Web Analysis: Developing a more robust presence to monitor and analyze content for investigative leads.  Specifications: State-of-the-art AI and ML capabilities to process vast amounts of data, extract meaningful insights, and enhance current analytical workflows. Focus on modularity and scalability.  Scope of Work: Develop and integrate AI/ML solutions into existing systems; configure and test equipment; provide training and support; assist in developing workflows and protocols for AI-powered analysis.  Contract Details: Expected contract value: $2.5M for an initial 2-year period, with 2 potential 2-year extensions. Firm-fixed-price.  Key Dates: Response deadline: 45 days from RFP release. Project kickoff: Within 3 months of contract award. Expected duration: 2 years, with possible extensions.  Evaluation Criteria: Technical approach (30%); past performance and experience (20%); cost-effectiveness (20%); delivery timeline (15%); quality of support and maintenance proposal (15%). Is there anything else I can help you with regarding this RFP or future ones? Here's the next one:     Federal Highway Administration (FHWA) Road Safety Procurement:  Procuring: Innovative solutions to enhance road safety and reduce traffic fatalities. Focus on technologies or systems that can identify and mitigate crash risks, especially in work zones.  Specifications: Robustness, portability, and ease of implementation are essential. Solutions should integrate advanced sensors, data analytics, and potentially autonomous vehicles to improve safety.  Scope of Work: Deployment of the solution across selected locations; data collection and analysis; real-time crash risk identification and mitigation; periodic performance reports.  Contract Details: Estimated value: $1M for an initial deployment phase. Potential multi-year follow-on contracts. Funding is through the Highway Safety Improvement Program (HSIP).  Key Dates: Responses due in 30 days; anticipated project start: mid-2023.  Evaluation Criteria: Life-saving potential (35%); effectiveness and relevance (25%); implementation feasibility (20%); cost-effectiveness (15%); past performance (15%). One moment while I locate the next file's contents.
    The Bureau of Reclamation, California Great Basin Region, seeks to evaluate a potential contractor's past performance. This two-page questionnaire focuses on the firm's history, including project details, completion dates, and contract compliance. The bureau requests that evaluators rate the firm's performance in multiple areas, such as client relationships, subcontractor management, and timeliness, using a scale of "Outstanding" to "Unacceptable." This information will help them assess the firm's suitability for future contracts. The bureau aims to gather comprehensive feedback to ensure informed decision-making during the vendor selection process.
    The Department of the Interior, Bureau of Reclamation, seeks to procure a comprehensive subcontracting plan from eligible offerors. The primary objective is to ensure the engagement of small businesses, including those owned by veterans, women, and historically underrepresented groups, in the execution of the contract. The plan should adhere to the Federal Acquisition Regulation (FAR) guidelines and encompass all necessary elements. Offerors are required to present a detailed breakdown of the types of supplies and services to be subcontracted, along with the respective small businesses that will provide them. The focus is on providing opportunities for equitable competition and ensuring compliance with subcontracting goals. The selected offeror will be responsible for administering the subcontracting plan, with a designated individual managing the program and ensuring timely reporting. This solicitation requests a good faith effort to include the small businesses involved in preparing bids or proposals, with a requirement to explain any deviations. Timely payments to small business subcontractors are emphasized, and a written explanation is needed if payments are reduced or delayed. The procurement process includes review and approval by several government representatives, indicating a thorough evaluation procedure. The estimated value of this contract is not explicitly mentioned in the files provided, and the focus is predominantly on the subcontracting plan and small business inclusion. Offerors are expected to submit their plans, ensuring compliance with the specified requirements, for evaluation by the Bureau of Reclamation.
    The Department of the Interior requires the contractor to furnish a release of all claims prior to receiving their final payment under the contract. The release discharges the United States and its employees from all liabilities and claims arising from the contract, with the exception of any explicitly excluded items. This legal document ensures the government's protection against any potential contractual disputes or claims. The contractor, having received the agreed-upon payment, confirms this release by signing and dating the document. Additionally, if the contractor is a corporation, the signature of an authorized representative is required to certify that the release was executed with valid corporate authority.
    Amendment 0002 relates to an ongoing federal request for proposals (RFP) or grant application process. Although the document does not provide specific details, it signifies an official update or clarification regarding the solicitation. Such amendments typically serve to convey additional information, changes to requirements, or adjustments in timelines that affect potential bidders or grant applicants. This could include modifications in eligibility criteria, submission guidelines, or budgetary constraints. The amendment is a crucial component of maintaining transparency in the procurement process while ensuring that all parties have access to the most current and relevant information, which promotes fair competition and compliance with federal regulations.
    The document pertains to the Request for Proposal (RFP) regarding the replacement of Generator Step-Up (GSU) transformers at multiple power plants as part of the Trinity River Division of the Central Valley Project in California. The solicitation number is 140R2024R0002. Key inquiries and responses from a pre-bid site visit are detailed, addressing contractor concerns, site requirements, logistics, and operational specifications. Major topics include the fixed pricing concerns for transformers, equipment logistics for moving and storing transformers, containment requirements during removal, transformer design specifications, and normalization of installation procedures across different plants. Importantly, the document outlines that the contractor is responsible for equipment and containment, specifies transformer fluid requirements, and emphasizes safety protocols. Furthermore, it details construction site management, including the necessity of proper anchoring systems and interface cabinet compatibility across all locations. Overall, the document serves to clarify essential aspects of the project and ensure that potential contractors understand the obligations and expectations tied to the transformer replacements within this federal grant framework.
    The Trinity River Division is seeking proposals for the replacement of GSU transformers as part of the Central Valley Project in California under Solicitation No. 140R2024R0002. Key clarifications from a pre-bid site visit address various specifications, including the allowable duration of the contract, the design specifications for transformers allowing interchangeable installation across power plants, and shipping requirements for the units. Notably, the performance period was extended to 2900 days through an amendment. Clear guidelines are provided regarding impedance values for new transformers, with no weight restrictions on the units themselves, though bidders must ensure transportation route suitability. The specifications permit the use of alternative insulating fluids while ensuring compliance with established requirements. Lastly, a two-week extension was granted for submitting additional questions, ensuring potential bidders have ample time to clarify their concerns before the November 1, 2024 proposal deadline. This document serves as essential guidance in adhering to procurement regulations and technical specifications for contractors engaged in federal projects.
    The solicitation for the Trinity River Division GSU Transformer Replacements, referenced as Solicitation No. 140R2024R0002, has been amended to accommodate bidders' requests for an extension on the proposal due date. Originally set for November 1, 2024, the new deadline will be January 31, 2025. Various transformer manufacturers expressed their need for additional time to accurately quote the project due to design complexities. The amendment addresses multiple requests for extensions, all leading to the same revised proposal due date. The document highlights the urgency and importance of ensuring that bidders can provide comprehensive and accurate proposals, reflecting the federal government's commitment to facilitating fair competition in the bidding process. This adjustment serves to enhance the bidding process's transparency and effectiveness within the scope of federal government RFPs.
    The Bureau of Reclamation's Mid-Pacific Region issues a contract amendment, titled "Trinity River Division GSU Transformer Replacements." The amendment focuses on updating instructions for obtaining drawings and revising contract sections. It removes Solicitation 140R2024R0002 and replaces it with the amended version, 140R2024R0002_0001. This administrative change does not alter the contract's essential purpose, which remains the replacement of transformers within the Trinity River Division. Offerors are required to acknowledge receipt of this amendment and must adhere to the specified hour and date for offer submissions. The amendment also emphasizes the importance of acknowledging the change, noting consequences otherwise. This amendment does not alter the contract's value or scope of work; therefore, the original terms and conditions remain in effect.
    The amendment to solicitation number 140R2024R0002 pertains to the replacement of transformers at the Trinity River Division GSU. It primarily aims to integrate a site visit sign-in sheet, address questions raised during the site visit, and extend the project's performance period. Additionally, it includes a revised PDF of the solicitation that features bookmarks for ease of navigation and updates to specification references in line with current Reclamation Safety and Health Standards. The amendment emphasizes that acknowledgment of receipt for the changes must be done by all contractors through specified methods prior to the submission deadline. Overall, this modification ensures clarity and compliance while facilitating contractor participation in the procurement process linked to critical infrastructure upgrades under the Bureau of Reclamation's jurisdiction.
    This document is an amendment to the solicitation 140R2024R0002 for the Trinity River Division GSU Transformer Replacements project. It specifies that offers must acknowledge receipt of this amendment prior to the submission deadline, using designated methods including a signed copy or electronic communication. The purpose of this amendment is to address questions from contractors and extend the deadline for inquiries. Proposed changes include the incorporation of responses to bidders' questions and an update to the solicitation document, now referenced as Amendment 003. This amendment does not alter other terms and conditions of the existing contract. These procedures ensure clarity and compliance in the federal procurement process while facilitating contractor participation. Ultimately, this amendment aids in promoting transparency and improving communication between the government and contractors involved in this project.
    The document is an amendment to the solicitation numbered 140R2024R0002 for the Trinity River Division GSU Transformer Replacements project. Its primary purpose is to address bidders' inquiries and extend the proposal submission deadline. Key changes include the incorporation of Attachment 8 into Section J and the replacement of previous Amendment 003 documentation with Amendment 004 for both Sections A and J. The amendment mandates that bidders acknowledge receipt of this change to ensure their offers are considered, emphasizing the requirement for this acknowledgment to be in place by the specified deadline. The document retains the overarching terms of the solicitation while integrating specific alterations to support the bidding process. Overall, this amendment is a procedural tool aimed at updating and clarifying details essential for contractors participating in the bidding for government contracts.
    The Bureau of Reclamation issues an invitation for bids (IFB) to undertake transformer replacements at multiple powerplants in California's Shasta County and Trinity County. The work involves significant electrical infrastructure upgrades, including performance requirements mandating adherence to strict technical specifications. The estimated contract value ranges from $35 million to $50 million. Bids are sought for the supply and installation of the specified transformers, with successful bidders expected to complete the project by March 31, 2027. The government intends to award a fixed-price contract to the highest-ranked bidder, evaluating offers primarily based on price and the ability to meet stringent technical requirements. Key dates include a site visit scheduled for November 1, 2024, and a submission deadline of 90 calendar days after this visit.
    The U.S. Department of the Interior seeks bids for the Trinity River Division GSU Transformer Replacements project in California's Central Valley. The primary objective is to replace nine in-service power transformers across three power plants: Spring Creek, Judge Francis Carr, and Trinity Powerplant. The transformers, along with associated components like surge arresters and bus systems, will be supplied, installed, and commissioned by the successful bidder. The project entails asbestos abatement, removal of existing transformers, and modifications to the isolated phase bus. Offerors must propose prices for four distinct powerplant sites, with warranted characteristics detailed for each transformer. Key requirements include adhering to work restrictions, using a contract document management system, and attending coordination meetings. The estimated value ranges from $35 to $50 million, and the contract will be awarded based on the lump sum prices for each site. Submission deadlines are outlined, with the contract scheduled to begin in November 2024. Evaluation criteria focus on the technical merit and price competitiveness of the proposed transformers and associated services.
    The U.S. Department of the Interior's Bureau of Reclamation seeks bids for the Trinity River Division GSU Transformer Replacements project in California's Central Valley Project. The primary objective is to replace nine in-service power transformers across three power plants, ensuring uninterrupted power generation during the replacement process. Transformors will be supplied, installed, and commissioned, while existing ones will be removed and disposed of safely. The work entails asbestos abatement, providing new transformer anchorage systems, and modifying existing isolated phase buses. The project requires a detailed construction program using the Critical Path Method and a web-based Contract Document Management System for efficient document control and tracking. Contractors must adhere to strict safety and environmental guidelines, coordinating closely with the government during the transformation process. The estimated value of this unrestricted procurement falls between $35 million and $50 million. Offerors must submit their bids by the specified deadline, with evaluations based on the offered prices and compliance with technical requirements. Key dates include a pre-design coordination meeting within 90 days of the notice to proceed, weekly progress reviews, and targeted interruption of service windows for each power plant.
    The U.S. Department of the Interior has issued a Request for Proposal (RFP) for the replacement of Generator Step-Up (GSU) transformers across three power plants in the Central Valley Project, California. This is part of the Trinity River Division's efforts to modernize infrastructure, with an estimated budget ranging from $35,000,000 to $50,000,000. The work involves supplying, removing, and installing nine transformers with specific site locations in Shasta and Trinity counties. Additionally, the project mandates tasks related to asbestos abatement and transformer anchorage system installations. The RFP outlines a comprehensive document structure, including solicitation details, pricing schedules, and description specifications. Key requirements include coordination meetings, construction schedules, and a Contract Document Management System (CDMS) for efficient project tracking and documentation. The proposal emphasizes maintaining operational access to the facilities and includes specific work restrictions and interruption guidelines to minimize service disruptions during construction. This solicitation aims to achieve high-efficiency outcomes while adhering to regulatory standards and operational constraints within the Bureau of Reclamation's oversight.
    The U.S. Department of the Interior issued Amendment 003 for Solicitation No. 140R2024R0002, pertaining to the replacement of Generator Step-Up (GSU) transformers at three power plants in Northern California: Spring Creek, Judge Francis Carr, and Trinity Powerplants. This $35 million to $50 million project involves supplying, installing, and removing transformers, modifying existing systems, and ensuring compliance with health and environmental standards. The document outlines procedural requirements, including site visit protocols, pricing schedules across multiple components, and evaluations based on comprehensive technical specifications. Offerors must complete all price schedules for consideration, ensuring no partial bids are accepted. Key responsibilities include managing construction coordination and maintaining operational access to power facilities during service interruptions. Additionally, contractors must submit regular status updates, including a Construction Program based on the Critical Path Method to manage timelines effectively. The solicitation encapsulates the government's aspiration to enhance power generation efficiency while adhering to safety and regulatory protocols, guiding contractors through a structured bidding process aimed at transparency and accountability.
    The U.S. Department of the Interior has issued a Request for Proposal (RFP) for the replacement of Generator Step-Up (GSU) transformers at three power plants within the Central Valley Project, California, outlined under Solicitation No. 140R2024R0002. The project includes the supply, removal, and installation of three transformers at each location: Spring Creek, Judge Francis Carr, and Trinity Powerplants, with an estimated total cost between $35 million and $50 million. The work must occur during specified service interruption windows to ensure minimal disruption in power generation. Offerors are required to submit comprehensive bids addressing all project components, including mobilization, asbestos abatement, and proper disposal of existing equipment. The proposal process emphasizes the importance of performance bonds, compliance with safety regulations, and adherence to detailed scheduling and inspection requirements. The contractor will also need to effectively manage all contract documents via a digital system, ensuring secure operations throughout the project lifecycle. This RFP illustrates the federal government's commitment to maintaining and upgrading critical infrastructure while promoting transparency and efficiency in procurement processes.
    Similar Opportunities
    K--Nathaniel "Nat" Washington Power Plant GSU Transformer Replacements
    Active
    Interior, Department Of The
    The U.S. Department of the Interior, through the Bureau of Reclamation, is seeking qualified contractors for the replacement of Generator Step-Up (GSU) transformers at the Nathaniel "Nat" Washington Power Plant, part of the Columbia Basin Project in Washington. The project involves supplying and installing six new 276 MVA outdoor step-up transformers, removing existing units, and modifying associated systems, with a focus on using synthetic ester fluid insulation and adhering to specific technical standards. This procurement is critical for modernizing the power plant's infrastructure and ensuring continued operational efficiency, with an estimated project value between $100 and $150 million. Interested firms are encouraged to submit their qualifications by February 14, 2025, and participate in an Industry Day scheduled for January 28, 2025, with registration required by January 14, 2025. For further inquiries, contact Scott Cooper at smcooper@usbr.gov or call 208-378-5104.
    Wolf Creek GSU Replacement
    Active
    Dept Of Defense
    The Department of Defense, through the U.S. Army Corps of Engineers, is soliciting proposals for the replacement and installation of Generator Step-Up (GSU) transformers at the Wolf Creek Power Plant in Jamestown, Kentucky. This procurement involves a firm-fixed-price hybrid supply-construction contract for the design, manufacture, testing, and delivery of three high-capacity power transformers, along with associated installation services. The project is critical for enhancing the power distribution capabilities of the facility and is estimated to have a contract value between $25 million and $100 million. Interested contractors must submit their proposals electronically via PIEE.gov by 2:00 PM Central Time on December 4, 2024, and are encouraged to direct inquiries to the primary contact, Andrew Roth, at andrew.r.roth@usace.army.mil.
    61--Nimbus Station Service Replacement
    Active
    Interior, Department Of The
    The Bureau of Reclamation, part of the Department of the Interior, is seeking proposals for the Nimbus Station Service Replacement project, specifically for the procurement and installation of critical electrical infrastructure components. The project requires the supply of various electrical equipment, including secondary unit substations, motor control centers, transformers, and circuit breakers, aimed at enhancing operational capacity and safety at the Nimbus Powerplant. This initiative is vital for maintaining and upgrading the electrical distribution systems within the Central Valley Project, ensuring compliance with federal standards and promoting small business participation. Interested contractors must submit their bids by December 13, 2024, at 5:00 PM PST, and can direct inquiries to Charlesetta Seibure at cseibure@usbr.gov or by phone at 916-978-5456.
    Pre-Solicitation Notice: Transformer Three Replacement, Bull Shoals Powerhouse
    Active
    Dept Of Defense
    The Department of Defense, through the U.S. Army Corps of Engineers (USACE) Little Rock District, is preparing to solicit proposals for the replacement of Transformer Three at the Bull Shoals Powerhouse. This project involves the removal and replacement of the existing transformer with a new three-phase gas-insulated GSU 120,000 kVA transformer, and will be conducted under full and open competition, encompassing both supply and construction components. The contract, which is expected to fall within a magnitude of $1 million to $5 million, will be awarded based on a Best Value - Trade Off evaluation method, with the solicitation anticipated to be issued around November 22, 2024. Interested contractors must be registered with the System for Award Management (SAM) and are encouraged to direct any inquiries to Sarah Hagood at sarah.n.hagood@usace.army.mil or by phone at 501-340-1277.
    Z--Reclamation - Interior Region 10 California - Great Basin (CGB) Region has a ne
    Active
    Interior, Department Of The
    The Department of the Interior's Bureau of Reclamation is preparing to issue a Request for Proposal (RFP) for the B.F. Sisk Dam Safety of Dams Modifications, Phase II project, located near Los Banos, California. This procurement involves significant construction efforts, including the construction of shear keys and berms, development of quarries for material sourcing, and installation of drainage systems, with an estimated project cost ranging from $250 million to $500 million. The contract will be awarded based on the best value proposal, and the performance period is expected to last approximately three years. Interested contractors must register in the System for Award Management (SAM) and obtain a Unique Entity Identifier (UEI), with the RFP anticipated to be released around November 12, 2024, and proposals due by January 13, 2025. For inquiries, contractors can contact Roxana Ahola at rahola@usbr.gov.
    Series Capacitor Bank Design-Build Project
    Active
    Energy, Department Of
    The Department of Energy, through the Western Area Power Administration (WAPA), is seeking qualified contractors for a fixed-price Design-Build contract focused on the replacement of four banks of 525-kV series capacitors as part of the California Oregon Transmission Project (COTP). The project entails engineering, procurement, and construction (EPC) services to remove and replace existing series capacitor banks, ensuring full integration with WAPA's existing substation infrastructure. This initiative is critical for maintaining the reliability and efficiency of the transmission lines, with an estimated construction value ranging from $75 million to $125 million and a completion deadline set for June 30, 2033. Interested firms are encouraged to submit their qualifications and bonding capabilities to Angela Xavier via email by November 18, 2024, at 10:30 am Pacific Time.
    Y--Archimedes pump construction for Topock
    Active
    Interior, Department Of The
    The U.S. Department of the Interior, through the Bureau of Reclamation, is soliciting proposals for the construction of a 60 cubic feet per second (cfs) pumping station at Topock Marsh within the Havasu National Wildlife Refuge in Mohave County, Arizona. The project involves the installation of an Archimedes Screw Pump, concrete structures, electrical systems, and modifications for solar power integration, with an estimated cost ranging from $10 million to $15 million. This initiative is crucial for enhancing local water management capabilities and supporting ecological preservation efforts in the region. Interested contractors must submit their proposals by November 21, 2024, and can direct inquiries to Diane Rodriguez at DLRodriguez@usbr.gov or by phone at 702-293-8368.
    Island Creek Switchyard Transformer
    Active
    Dept Of Defense
    The U.S. Army Corps of Engineers, Wilmington District, is soliciting proposals for the design, manufacture, testing, and delivery of two outdoor Class II oil-filled three-phase transformers and associated electrical equipment for the Island Creek Switchyard project in Boydton, Virginia. The contract requires the provision of transformers rated at 5,000 kVA, along with circuit switchers and load-break switches, all designed to enhance the operational capacity of the pumping plant while adhering to federal and local regulations. This procurement is set aside for small businesses, emphasizing the importance of small business participation in federal contracting. Interested parties must submit their proposals by December 6, 2024, and can direct inquiries to primary contact Jenifer Garland at jenifer.m.garland@usace.army.mil or secondary contact Troy Small at troy.d.small@usace.army.mil.
    Procurement of New Transformer, Current Supporting 800kW, 60 Hz DPGDS
    Active
    Dept Of Defense
    The Defense Logistics Agency (DLA) is seeking sources for the procurement of a new transformer, specifically the Transformer, Current Supporting 800kW, 60 Hz DPGDS, on behalf of the Army Integrated Logistics Supply Center (ILSC). The government intends to acquire a total of 90 units over a five-year period, with specific quantities required each year, and is looking for suppliers who can provide detailed information on lead times, cost estimates, production capacity, and relevant documentation to support their capabilities. This transformer is critical for military operations, and the selected contractor must demonstrate experience in similar technologies and the ability to meet U.S. government delivery timelines. Interested parties must submit their responses by January 14, 2025, to the designated contacts, Mr. Lawrence Donohue and Mr. Micah Greene, via the provided email addresses.
    Z--Hyrum Dam Spillway Replacement
    Active
    Interior, Department Of The
    The Bureau of Reclamation, part of the U.S. Department of the Interior, is soliciting bids for the Hyrum Dam Spillway Replacement project located near Hyrum City, Utah. The project involves the construction of a new spillway, removal of the existing spillway, and various associated infrastructure improvements, including drainage systems, mechanical features, and roadway realignment. This initiative is critical for enhancing dam safety and operational efficiency, reflecting the government's commitment to maintaining and improving water resource management infrastructure. Interested contractors must submit their proposals by November 13, 2024, and can direct inquiries to Lynette Rock at LRock@usbr.gov or by phone at 385-228-8535. The anticipated contract value is estimated between $100 million and $200 million, with the performance period extending from March 2025 to January 2029.