ContractCombined Synopsis/SolicitationTotal Small Business Set-Aside (FAR 19.5)

B254 Mezzanine Repair at Pease ANGB

DEPT OF DEFENSE W50S8A26QA008
Response Deadline
May 29, 2026
9 days left
Days Remaining
9
Until deadline
Set-Aside
Total Small Business Set-Aside (FAR 19.5)
Notice Type
Combined Synopsis/Solicitation

Contract Opportunity Analysis

The Department of Defense, through the Army’s New Hampshire Air National Guard, is seeking quotes to repair the B254 mezzanine at Pease Air National Guard Base. The work calls for providing and installing three C-channel steel beams beneath the equipment housekeeping slab and welding them to the existing wide flange beams to reinforce the mezzanine structure. The project is a total small business set-aside, will be performed in Newington, New Hampshire, and includes requirements tied to structural welding standards, government site access, and use of a certified welding inspector. Quotes are due by 29 May 2026 at 4:00 PM Eastern, questions are due by 15 May 2026 at noon Eastern, and a site visit is scheduled for 12 May 2026 at 0900 with attendee information due by 8 May 2026 at 4:00 PM; SAM registration must be active at award.

Classification Codes

NAICS Code
238120
Structural Steel and Precast Concrete Contractors
PSC Code
9640
IRON AND STEEL PRIMARY AND SEMIFINISHED PRODUCTS

Solicitation Documents

8 Files
AMENDMENT- 1 SITE VISIT.pdf
PDF54 KBMay 20, 2026
AI Summary
AMENDMENT 1 announces a site visit for a mezzanine installation project at Pease ANGB on May 12, 2026, at 0900. This visit allows potential offerors to view the facility. Questions will not be answered during the visit but should be submitted to the listed Points of Contact (POCs) afterward. To accommodate potential inquiries, the Request for Information (RFI) period is extended from May 5, 2026, to May 15, 2026. Attendees must submit their names and contact information by 4:00 PM on May 8, 2026, to Casey Pridham and Matthew Lapointe. Participants must arrive 15 minutes early at the North Gate, will be escorted to the worksite, and require a Real-ID (passport or compliant license) for access.
Site Visit Sign in Sheet.pdf
PDF18 KBMay 20, 2026
AI Summary
The document is a sign-in sheet for a site visit related to the W50S8A-26-Q-A008 B254 Mezzanine Repair project. It lists attendees from various companies, including Rothwell Construction, Vedant Construction, Vedoni Construction, and O'Leary Welding, along with their contact information (phone number and email). The sheet also indicates whether each company is a prime contractor. This document serves as a record of participation in a site visit, likely a mandatory or highly recommended event for potential bidders on a government Request for Proposal (RFP) for construction or repair services.
Clauses and Provisions_W50S8A26QA008_UPDATED.pdf
PDF97 KBMay 20, 2026
AI Summary
This government file, W50S8A26QA008, outlines various clauses incorporated into federal contracts, primarily focusing on Department of Defense (DoD) procurements, as well as general federal acquisition regulations. Key areas addressed include prohibitions related to compensation of former DoD officials, whistleblower rights, safeguarding covered defense information, and restrictions on acquiring covered defense telecommunications equipment and services, particularly from specific regions or entities (e.g., the Maduro Regime, Xinjiang Uyghur Autonomous Region). The document also details instructions for electronic payment submissions via Wide Area WorkFlow (WAWF), including definitions, access procedures, training, document types, and routing information. Furthermore, it incorporates clauses regarding prohibitions on contracting with corporations having delinquent tax liabilities or felony convictions. For time-and-materials or labor-hour contracts, specific terms for inspection, acceptance, and payments are detailed, including hourly rates, material reimbursement, total cost limitations, and conditions for termination for convenience or cause.
Mezzanine RFIs_5 MAY 26.xlsx
Excel11 KBMay 20, 2026
AI Summary
This government file details a series of questions and responses regarding a federal project involving work on a mezzanine. Key clarifications include the contractor's responsibility to provide a Certified Welding Inspector (CWI) for structural welds, confirmation of the mezzanine height at 20' 4-1/2", and the government's stance on lift equipment – contractors must select equipment suitable for the space, though all government equipment beneath the mezzanine will be removed. The government will also handle updates to construction drawings, relieving the contractor of providing as-built drawings. Images of the work area are provided as reference, but contractors are advised to attend a site visit for accurate assessments. The document emphasizes contractor responsibility for equipment selection and welding inspection, while the government manages drawing updates and site preparation.
SoW B254 Structural Repair FINAL.pdf
PDF91 KBMay 20, 2026
AI Summary
This Statement of Work (SOW) outlines the requirements for delivering and installing a steel substructure for the mechanical mezzanine at Building 254. The project addresses an issue where a circulator pump and hydro-pneumatic tank exceeded the mezzanine slab's design capacity. The contractor will install three C-channel steel beams beneath the equipment's concrete housekeeping pad to reduce stress on the slab. The work involves providing materials, fabricating structural members, and welding the new beams to existing members, adhering to AWS D1.1:2025 standards. Special requirements include obtaining a hot work permit from the Pease Fire Department and submitting documentation for base access and badging within 10 days of contract award. Work hours are Monday through Friday, 0600-1530, with specific rules for off-hour work and federal holidays.
Provisions and Clauses_W50S8A26QA008.pdf
PDF110 KBMay 13, 2026
AI Summary
The document W50S8A26QA008 outlines various clauses and regulations for federal government contracts, particularly for the Department of Defense. Key areas covered include prohibitions on acquiring covered defense telecommunications equipment from certain sources, detailed instructions for electronic payment submissions via Wide Area WorkFlow (WAWF), and representations regarding delinquent tax liabilities or felony convictions for contracting corporations. It also specifies terms and conditions for commercial products and services, including inspection, acceptance, and payment procedures for time-and-materials or labor-hour contracts. The document emphasizes compliance with safeguarding defense information, whistleblower rights, and restrictions on business operations with specific regimes or regions. Evaluation factors for contract awards, economic purchase quantity considerations, and a program for agency protests within the National Guard Bureau are also detailed.
Attachment 1 - NHANG Hgr 254 Mezz 42C PWP-1 Location Mitigation.pdf
PDF4873 KBMay 20, 2026
AI Summary
The document outlines plumbing floor plans for the KC-46A ADAL Maintenance Hangar, Building 254, at Pease Air National Guard Base, New Hampshire. It details mechanical mezzanine and existing mezzanine restroom plumbing, including pipe diameters for various systems like chilled water (CW), condensate, sanitary sewer, and gas (G). Key notes indicate that new fixtures will replace existing ones, requiring reconnection to existing piping and wall refinishing. Lavatory sinks will retain existing faucets, with only faucets being replaced and walls refinished. Shower pans will remain, with only shower heads and valves replaced. The plans include routing instructions for condensate and sanitary sewer piping, emphasizing field location and tie-ins to existing services. Revisions note compressor location and mezzanine equipment adjustments.
RFI_Mezzanine structural repairs photos.pdf
PDF2718 KBMay 20, 2026
AI Summary
The document outlines the logistical and structural considerations for reinforcing a mezzanine area, likely as part of a government construction or renovation project. It details site preparation, including clearing government equipment from the work area, and grants the contractor access via an adjacent roll-up door. Material and equipment storage is permitted under the mezzanine during work hours. The document also provides approximate locations of three new beams, noting their placement against the slab and confirming that existing conduit will not interfere due to its depth. Additionally, it references several penetration locations for contextual understanding in other related photos, covering under-slab and equipment room areas. This information is crucial for planning and executing the reinforcement work while minimizing disruption and ensuring structural integrity.

Related Contract Opportunities

Project Timeline

postedOriginal Solicitation PostedApr 24, 2026
amendedAmendment #1· Description UpdatedApr 29, 2026
amendedAmendment #2May 5, 2026
amendedAmendment #3· Description UpdatedMay 13, 2026
amendedLatest Amendment· Description UpdatedMay 20, 2026
deadlineResponse DeadlineMay 29, 2026
expiryArchive DateJun 13, 2026

Agency Information

Department
DEPT OF DEFENSE
Sub-Tier
DEPT OF THE ARMY
Office
W7NN USPFO ACTIVITY NHANG 157

Point of Contact

Name
Casey Pridham

Place of Performance

Newington, New Hampshire, UNITED STATES

Official Sources