Lenel Access Control System Installation for SCIF Environment
Contract Opportunity Analysis
The Department of the Air Force, 86th Airlift Wing, is seeking a firm-fixed-price solution for the FY26 installation of a Lenel access control system for a SCIF environment at Ramstein Air Base, Germany. The work covers provision and installation of door hardware, Lenel OnGuard system components, cabling infrastructure, system programming and configuration, testing, and administrator-level training. Key requirements include a stand-alone system, a U.S.-made desktop computer, CAC enrollment capability, EMT conduit for cabling, EU-compatible backup power, and installation by contractors with top secret clearance who are U.S. citizens. Quotes are due by June 22, 2026, at 3:00 PM CET, must be submitted in USD by email to Giuseppe Di Fede and Cole West, remain valid for 180 days, and include the required DD Form 254 and supporting vendor information.