Y--GRCA 318719_Temporary WWTP at North Rim
Contract Opportunity Analysis
The National Park Service Denver Service Center is soliciting proposals for project GRCA 318719 to install and operate a temporary wastewater treatment plant at the Grand Canyon National Park North Rim. The scope of work requires constructing a 90,000 gallons per day membrane wastewater treatment system including site grading, utility connections, headworks, two 45,000 gallons per day MBR treatment units, UV disinfection, chemical storage, and a mobile laboratory, followed by six months of operational support. Prospective contractors must complete construction, testing, and obtain Arizona Department of Environmental Quality operational approval by June 1, 2027, within an overall performance period of 420 calendar days from the notice to proceed. This small business set-aside opportunity has an estimated construction magnitude exceeding $10 million, and proposals must be submitted by July 29, 2026, at 12:00 PM MDT to James Waller at james_waller@nps.gov.