Weeks Brook Bridge Railing Repair, Franklin Falls Dam, Sanbornton, NH
Contract Opportunity Analysis
The U.S. Army Corps of Engineers, under the Department of the Army, is seeking a small business contractor to repair the Weeks Brook Bridge railing at Franklin Falls Dam in Sanbornton, New Hampshire. The work requires removal of the existing bridge railing and posts and installation of a new railing system anchored to the bridge superstructure in accordance with project drawings and New Hampshire Department of Transportation standards. The project also calls for compliance with USACE safety requirements, including EM 385-1-1, an Accident Prevention Plan, an Activity Hazard Analysis, and a qualified Site Safety and Health Officer, with a 150-day performance period from notice to proceed. The estimated construction magnitude is between $25,000 and $100,000, and vendors must have an active SAM.gov registration to be considered.