Storm Water Retention Pond Rehabilitation
Contract Opportunity Analysis
The U.S. Geological Survey, Office of Management Services, has a requirement for storm water retention pond rehabilitation at the USGS National Center in Reston, Virginia. The contractor will be responsible for restoring the facility's 0.3-acre wet pond to its original design capacity, which includes removing sediment and vegetation without damaging the liner, repairing mechanical components, and calculating nutrient loading reductions. Work must be completed within 90 calendar days of award, adhere to GSA and OSHA safety regulations, and carry a one-year warranty on all labor and materials. This procurement is a Women-Owned Small Business set-aside, evaluated on a best-value basis of price and past performance, with quotes due by September 18, 2026, at 5:00 PM Eastern Time to Contracting Officer Leah Williams at leah_williams@ios.doi.gov.