Y--2026 MARCOTT COULEE PIPELINE
Contract Opportunity Analysis
The Department of the Interior, Bureau of Land Management, Montana State Office intends to solicit proposals for the construction and installation of the Marcott Coulee Pipeline stock-water delivery system in Fergus County, Montana. The selected contractor will furnish all labor, equipment, and materials to trench and bury 53,233 linear feet of 2-inch HDPE pipe to a depth of six feet, and install multiple water trough, watering, air relief valve, and curb stop valve assemblies. On-site construction is restricted to a permitted window between July 15 and November 30 to protect local wildlife, and the system must undergo rigorous hydrostatic pressure and flow testing prior to completion. Potential sources are invited to submit capabilities statements, company details, and feedback on the specifications via email to jalvarez@ios.doi.gov by August 4, 2026, for this project valued between $250,000 and $500,000.