Y--Speelyi Shoreline protection
Contract Opportunity Analysis
The Bureau of Reclamation is seeking bids for the Speelyi Beach Shoreline Protection project at Cle Elum Reservoir in Kittitas County, Washington. The selected contractor will construct shoreline protection through tasks including earthwork, riprap placement, site grading, perch beach zoning, temporary access road creation, and the installation of fish habitat log structures. All excavation work must be performed "in the dry" when reservoir levels are low, and the contractor must finalize draft water quality, erosion control, and spill prevention plans at least 28 days before starting. This opportunity is a total set-aside for Indian Small Business Economic Enterprises (ISBEE) with an estimated project value between $1,000,000 and $5,000,000, and bids are due by July 22, 2026, at 1:00 PM MDT.