HUM MALSR Demo and Replacement
Contract Opportunity Analysis
The Federal Aviation Administration is seeking a contractor to demolish and replace the Medium Intensity Approach Lighting System with Rail (MALSR) at Houma-Terrebonne Airport in Houma, Louisiana. The work includes removal of the existing lighting system and related infrastructure and installation of a new Patriot MALSR system, along with associated power, control, shelter, access road, and site restoration work. The project requires full provision of labor, materials, equipment, and related construction services, with deliverables including redlines, technical reference data records, functional checkout, site acceptance testing, and an approved Safety Plan Compliance Document. A mandatory site visit is scheduled for May 6, 2026, offers are due May 25, 2026, and performance is to begin within 5 calendar days of the notice to proceed and be completed within 45 calendar days, with all construction finished by December 31, 2027.